After the floor plans have been finalized, we begin by installing the basement/foundation:
The basement walls are built, then we proceed with the installation of the 1st floor. Once the floor is finished, we build all of the decks.
Now we start stacking the logs!
All of our logs are notched and cut to precision lengths right on the job-site. This insures that our quality work is unmatched by anyone!
We also drill and notch for receptacles and switches.
After the logs are stacked, we install all of the 1st floor interior walls and the 2nd floor system.
Now we build the 2nd floor exterior walls and gables.
With the exterior walls complete, its time for the roof framing.
At this point, the staining can begin, along with the installation of the metal/shingle roofing, porch rails, and the window/door installation.
These are some of the basic steps we take to complete the exterior of a home. Inside the home will then consist of the electrical, plumbing, heating and air, and wall/floor covering.